Programs & Products

Distributed Generation

This program is applicable to customers desiring to sell electrical energy to Marietta Power produced by solar, wind, or fuel cell technology.

Safety, Power Quality, and Interconnections Requirements

The customer is responsible for ensuring a safe and reliable interconnection with Marietta Power and all costs incurred. The following three documents must be completed in their entirety and approved prior to interconnection.

  • Application for Interconnection of Distributed Generation Facility

  • Interconnection Agreement

  • Electrical Power Exchange Agreement

Qualifications

The distributed generation facility must:

  1. Be owned and operated by a customer of Marietta Power for production of electric energy, and

  2. Be located on the Customer's premises, and

  3. Be connected to and operate in parallel with Marietta Power's distribution facilities, and

  4. Be intended primarily to offset part or all of the Customer's generator's requirement for electricity, and

  5. Have peak generating capacity of not more than 10 kW for residential applications and not more than 100 kW for commercial applications, and

  6. Use solar photovoltaic system, fuel cell, or wind generation.

Pricing

Marietta Power will pay $.054 per kWh for excess energy generated by the customer.

 

Distributed Generation Policy

Application

Power Exchange Agreement